Project: Upgrade of Yola Airport to B727/B707 Standards in Yola Adamawa.
Main Contractor: Julius Berger Nigeria plc
Employer/Owner: Federal Ministry of Aviation
Project Status: Completed.
Scope of Work:
Removal of the existing failed Asphalt Surface. Widen of the existing Runway from 30m to 45m and also increasing the length from 2.5km to 3.5km.
Construction of a new Concrete Apron and Taxiway. Drainage Works. Laying of Binder and Wearing Course Asphalt on the entire Runway